St Andrew gets deep at Clavos

The decline at the Clavos project, east of Timmins, Ont., being driven by Dumas Contracting for owner St Andrew Goldfields (SAS-T), has reached the 200-metre level.

The ramp, now 1.2 km long, has drifts from the 100-, 150-, and 200-metre levels. The drifts have reached the Clavos mineralized zone and confirmed the grade and continuity of the zone, which had been known only from drilling. Some initial stoping, to provide bulk samples for mill testing, is under way.

St Andrew is drilling holes from the underground workings to confirm a minable reserve.

The Stock Twp. mill, which will receive the ore from Clavos, started pouring gold again in mid-September, using material from the Stock mine and from the development drifts at Clavos. Stock is scheduled to provide 300 tonnes of ore per day starting next month, and Clavos should be sending 700 tonnes per day at the same time, bringing the mill to full capacity.

St Andrew has had a series of personnel changes on its Timmins projects, including the departure of the general manager at the Stock Gold Complex, Stuart Green, at the end of October. Paul Jones, St Andrew’s executive vice-president of operations, has taken over responsibility for Stock. St Andrew has also added a manager for the Taylor mine project, Claude Schimper.

Print

Be the first to comment on "St Andrew gets deep at Clavos"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close