Edgewater hit by permitting delays

VANCOUVER — Regulatory approval has become murkier for Vancouver-based junior Edgewater Exploration (TSXV: EDW) at its Corcoesto gold project in Galicia, Spain.

Apparently it’s a chicken-and-egg type situation where the government wants money before permits, and the company needs permits to raise money.

On Oct. 16 the company acknowledged that the Galician government’s Ministry of Industry had communicated through local press that it would be freezing permit activities at Corcoesto due to the company’s failure to secure roughly US$40 million in financing.

The project had been proceeding under a “Special Strategic Process” designation designed to expedite its permitting timeline.
According to president and CEO George Salamis, Edgewater is close to completing a feasibility study at Corcoesto, but was unable to secure financing “in turbulent markets and without its permits.” Salamis added that dialogue with the government will continue, and reiterates that the decision does not rule out Corcoesto’s development.

At the time of writing Edgewater had yet to speak with Galician authorities directly.

Print

Be the first to comment on "Edgewater hit by permitting delays"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close