Waratah’s coal project nixed in Queensland (September 05, 2008)

An environmental ruling against Waratah Coal‘s (WCI-V, WGO-A) multi-billion dollar proposal for a major coal port development on the east coast of Australia has crushed the stock. At mid-day in Toronto, Waratah shares were down 61.9%, or $1.14, to 70 on 2.03 million shares traded.

Waratah had planned to build a thermal coal mine in the Galilee Basin linked by a new 495-km rail line to a purpose-built export facility on the Queensland coast.

In mid-July, Premier Anna Bligh endorsed the A$5.3 billion (US$4.6 billion) project and designated it of “state significance”a classification that is only given to critical infrastructure projects and is designed to help fast-track construction.

But today Federal Minister for Environment Peter Garrett rejected the proposal, ruling it “unacceptable” under Australia’s Environment Protection and Biodiversity Act.

Declaring that the environment minister had “exceeded his authority” and calling the decision “wrong in law” and “not in the national interest,” Waratah chief executive Peter Lynch says he will challenge the decision in Australia’s federal court.

Lynch argues that Queensland has much to gain from the ambitious project. Under current contract prices, the proposed mine and infrastructure project would potentially generate more than A$10 billion in export revenues and over A$900 million in royalties annually for the state, the company outlines in a press release.

The Aussie junior argues that the proposed port is the most attractive natural deepwater port location on Queensland’s coast and the new facility would be built to accommodate the 350,000-deadweight tonne Chinamax class bulk carriers.

Waratah had also planned to build a heavy haul, standard gauge rail system to support 21,000-tonne train units. The system was to be equipped with dual gauge rail from the Bowen Basin mining camp to the port to accommodate third-party users.

The Bowen Basin is home to projects owned by BHP Billiton (BHP-N, BLT-L), Anglo American (AAUK-Q, AAL-L), Xstrata (XSRAF-O, XTA-L), Rio Tinto (RTP-N, RIO-L), Vale (RIO-N, MacArthur Coal.

Waratah’s proposed open-pit mine in the Galilee basin would have an initial export capacity of 25 million tonnes annually and was expected to have started production in late 2012.

The coal would have been processed at an on-site facility north of the town of Alpha, 160 km west of Emerald. The processed coal was then be sent by rail to the planned export port facility.

Print

Be the first to comment on "Waratah’s coal project nixed in Queensland (September 05, 2008)"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close