Trevali prefeasibility expands Rosh Pinah mine in Namibia

Trevali Mining's Rosh Pinah zinc-lead-silver underground mine in Namibia. Credit Trevali Mining.

The results of Trevali Mining’s (TSX: TV; US-OTC: TREVF) prefeasibility study of an expansion of the Rosh Pinah zinc-lead-silver underground mine in Namibia to 1.3 million tonnes per year, up from 700,000 tonnes per year currently, shows the potential for increased production at lower operating costs starting in 2023.

The proposed 11-year mine would produce an average of 132 million lb. payable zinc, 21.8 million lb. payable lead and 286,000 oz. payable silver each year, at all-in sustaining costs (AISCs) of US$64¢ per lb. zinc. With a project capital cost estimated at US$93 million, the net present value estimate for the development is US$142 million, at an 8% discount rate and based on US$1.11 per lb. zinc, US93¢ per lb. lead and US$19.81 per oz. silver. The internal rate of return stands at 65%.

“Over Rosh Pinah’s 50-year operating life, the mine has processed close to 30 million tonnes, and today we have 16 million tonnes in resource, inclusive of reserves, with several advanced exploration targets ready to drill,” Ricus Grimbeek, the company’s president and CEO, said in a news release. “To match this exceptional orebody, the RP2.0 PFS recommends an 86% expansion to the existing production capacity by sizing the infrastructure to a nominal throughput of 1.3 million tonnes per annum.”

Grimbeek added that the resulting AISCs of US$64¢ per zinc lb. positions Rosh Pinah in the bottom half of the industry’s cost curve.

The study suggests upgrades to the comminution and processing circuits, as well as an additional portal and decline to the WF3 deposit, alongside a new paste fill plant and additional mobile equipment to increase throughputs and lower operating costs.

Grimbeek also suggested that the underground infrastructure and paste plant additions, as well as processing upgrades, would “allow us to modernize the mine and produce more metal faster and at a significantly lower operating cost, all while working more safely and reducing our environmental footprint.”

Trevali now plans to complete additional optimization work ahead of a feasibility study, which would start in the first quarter of next year.

Optimization opportunities include determining the best underground infrastructure placement, improving lead recoveries through additional flotation studies and upgrading inferred resources for scheduling optimization.

Any future construction would start in the first quarter of 2022, ahead of commercial production from the expanded operation in 2023.

As a result of the prefeasibility study, Trevali has updated the reserve and resource statements for Rosh Pinah. Reserves total 11.2 million tonnes, at 6.26% zinc, 1.33% lead and 19 grams silver per tonne, based on a US$104 per tonne net smelter return cutoff.

The 90%-owned Rosh Pinah mine has been operating since 1969 and produces zinc and lead sulphide concentrates, which also contain copper, silver and gold, shipped to spot markets off of the Namibian coast.

Last year, Rosh Pinah generated 92 million lb. payable zinc, 12.1 million lb. payable lead and approximately 200,000 oz. payable silver.

— This article first appeared in the Canadian Mining Journal.

Print

Be the first to comment on "Trevali prefeasibility expands Rosh Pinah mine in Namibia"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close