Tamerlane to Revive Pine Point

Vancouver — Tamerlane Ventures (TAM-V, TMLVF-O) is poised to develop a new mine on the site of one of Canada’s most successful base metals mines, with a positive feasibility study and updated reserve and resource estimates from the Pine Point project, in the Northwest Territories.

The new Pine Point project encompasses the site of the old Cominco Pine Point mine, which extracted more than 64 million tonnes of ore grading 7% zinc and 3.1% lead between 1964 and 1987 to make it the largest and most profitable zinc-lead mine in Canadian history. In the new project, Tamerlane plans to focus on developing the R-190 deposit underground mine, then use the R-190 infrastructure to access a series of nearby deposits with resources that have just been upgraded to the indicated category.

The R-190 deposit holds proven reserves of 1 million tonnes grading 11.16% zinc and 5.49% lead with a 5% zinc cutoff. Five additional deposits, which were not included in the feasibility study, contain indicated resources estimated at 10.9 million tonnes averaging 4.69% zinc and 2.43% lead. Historic resources point to another 51 million tonnes grading 3.8% zinc and 1.2% lead, but Tamerlane has not yet updated the figure to National Instrument 43-101 standards.

The 100%-owed Pine Point property sits on the south side of Great Slave Lake. Plans call for an underground, year-round mine, a vertical shaft and a vertical conveyer to hoist ore to the surface, mechanized long-hole stoping, and dense media separation with flotation to upgrade the zinc and lead concentrates.

A freeze curtain, a frozen ring of ice surrounding the entire R-190 deposit and underground infrastructure, will extend to a depth of 185 metres in order to prevent water from the aquifer from entering the underground workings. A primary crusher at the bottom of the shaft will size ore to less than 4 inches in diameter before entering the vertical conveyor, which will lift material at a rate of 160 tonnes per hour. Almost all waste will be returned underground to be used as backfill, eliminating the need for permanent tailings dams.

A highway passes within 500 metres of the project. Concentrate from the mine will be trucked to Hay River, 43 km away, and then loaded onto railcars. The project will be powered via hydroelectricity.

Construction is expected to take 12 to 15 months. Mining out the R-190 deposit will take the next 12 to 15 months, at which point Tamerlane will develop drifts to access the other deposits.

The total estimated capital cost of construction, including a 10% contingency fund, is $93.3 million. Initial working capital for the first 90 days of production will be roughly $33.9 million. In regular production, operating costs are expected to run at $53.29 per tonne mined, or 20 per payable pound of metal (total lead and zinc).

Using metal prices over the past 2- and 3-year periods averaged equally with the 15-month LME futures price, net cash flow is estimated at $52.7 million. Net cash flow increases to $93.1 million using 15-month LME contract prices alone. Using cash metal prices from market open on Aug. 21, 2007, net cash flow rises to $115.4 million.

Geologically, Pine Point is part of the Western Canada Sedimentary Basin and its deposits occur in mid-Devonian carbonate barrier complex as Mississippi Valley-type lead-zinc deposits. Karsting gave rise to three northeast-trending zones parallel to the strike of the barrier complex, and the resulting karst cavities host the mineralization.

Print

Be the first to comment on "Tamerlane to Revive Pine Point"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close