South Star targets late 2023 start for Brazil graphite mine

South Star secures construction permit for graphite mine in BrazilAerial view of the Santa Cruz graphite project. (Image courtesy of South Star Battery Metal.)

South Star Battery Metals (TSXV: STS; OTCQB: STSBF) says its Santa Cruz graphite project in eastern Brazil is on track to complete construction and commissioning by December next year.

Most large machinery has been contracted and the initial offices are to be completed by early January at the site in Bahia state about 670 km south of its capital, Salvador, the company said in a news release this week.

Production is to begin in an US$8-million first phase at a rate of 5,000 tonnes of concentrate per year from an open pit followed by US$27 million in upgrades to produce 25,000 tonnes a year, according to South Star. Phase one permits and licences are in place, it said.

The Vancouver-based company wants by early next year to submit plans to Brazil’s mining regulator for production to increase to 50,000 tonnes a year in a third phase, and file requests for environmental permits for phases two and three to municipal authorities, it said.

“Phase one commercial production is planned for December 2023,” chief executive Richard Pearce said in the release. “We are confident in delivering on our promise to be the first new graphite production in the Americas since 1996.” 

South Star is developing what may be the region’s largest industrial plant in the country second to China in graphite production. It’s seeking to tap into the surging demand for materials to make electric vehicle batteries and other green technologies for fighting climate change. South Star also has an early-stage graphite development project at a past-producing mine dating from World War II about 100 km north of Montgomery, AL.

The company says it expects permits and licences for Santa Cruz’s phases two and three to be approved late next year around when phase one operations are to start. 

The Santa Cruz project has an after-tax net present value of US$81.2 million with a 5% discount rate for an annual after-tax internal rate of return of 35%, according to a 2020 prefeasibility study. South Star calculated average operating costs for the 12-year life of the mine at US$396 per tonne of concentrate and used a price of US$1,287 per tonne of concentrate. 

The project has proven and probable reserves of 12.3 million tonnes grading 2.4% graphitic carbon for 295,400 tonnes in-situ graphite.

South Star shares gained 2¢ to 49¢ apiece at midday Thursday in Toronto, valuing the company at $15 million. Its shares have traded in a 52-week window of 37¢ and $1.80.

Print

Be the first to comment on "South Star targets late 2023 start for Brazil graphite mine"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close