Preliminary economic studies on the Mina Justa copper project in southwestern Peru have indicated an open-pit mine could be feasible.

Chariot Resources (CHD-T), which owns a 70% interest in the project, commissioned the study by consulting firm GRD Minproc. Minproc modelled the economics of a start-up heap leach operation with follow-on construction of a mill.

Minproc concluded the project had a pre-tax net present value of US$364 million, based on an 8% discount rate, with an internal rate of return of 28%. The initial capital cost to bring the heap leach operation on stream would be around US$236 million.

The mine would exploit an oxide resource of 121 million tonnes at 0.62% copper and a sulphide resource of 21 million tonnes grading 2% copper. A preliminary pit design puts the stripping ratio at 2.5. Three-fifths of the resource is currently only inferred, and more drilling will be needed before a full feasibility study can be done.

Minproc estimated the production costs at US$1,520 per tonne (US69 per lb.), a figure that did not include any by-product credits. Chariot plans to produce both silver and a magnetite concentrate from Justa, as well as an average 70,000 tonnes copper annually.

Chariot owns 70% of the Marcona copper project, of which Justa is a part. Korea Resources Corporation and LG-Nikko Copper are joint venture partners.

Print

Be the first to comment on "Positive early assessment for Mina Justa"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close