Orvana rises on Copperwood PEA (September 14, 2010)

Vancouver – Orvana Minerals (ORV-V) has released a preliminary economic assessment for its Copperwood project in Michigan, marking three early-stage mine plans in as many months.

In July the company released reserve and financial data on its El Valle-Boinas/Carles gold project in Spain, and in August Orvana outlined details for its Upper Mineralized Zone copper-gold-silver project in Bolivia.

For the Copperwood project, the study outlined an underground operation using room-and-pillar mining to produce copper and silver. The study looked at conventional drill-and-blast, roadheader and continuous miner methods and settled on continuous mining to reduce costs despite possibly higher dilution.

In March Orvana released a resource estimate for Copperwood that incorporated both the dark-grey siltstone and black laminated shale Domino unit, and the red-massive, grey-laminated siltstone Upper Layer. Combined, the resource contains 19.47 million measured and indicated tonnes grading 1.86% copper for 798 million contained lbs. The resource contains a further 3.27 million inferred tonnes grading 1.49% copper, all using a 1% copper cut-off grade. Copper occurs as very fine-grained chalcocite.

The conceptual mine plan, meanwhile, incorporated 16 million tonnes grading 1.51% copper. At a throughput of 1.6 million tonnes per year, or roughly 4,500 tonnes a day, the plan establishes a 10-year mine-life. With copper recovery estimated at 85% using froth flotation, the mine is expected to produce 20,000 tonnes of copper and 103,000 oz. silver per year.

The mine is expected to cost US$143.3 million in pre-production capital, including a US$25 million contingency, while working and sustaining capital is pegged at US$87.1 million.

The study put a net present value of US$128.1 million on the project using a long-term copper price of US$2.25 per lb. and US$14 per oz. silver, and a 5% discount rate. With the same prices, the internal rate of return works out to 20.2% with a 4.4 year payback period. Using a copper price of $3.25 per lb., closer to the current spot price of around US$3.44 per lb., the IRR works out to 41% with a payback period of 3 years, and the NPV jumps to US$390 million.

The company plans to apply for a mining permit next spring, and has been encouraged by the recent permitting of Rio Tinto‘s (RIO-L) Eagle nickel-copper mine in the state.

Orvana has long-term mineral leases covering 712 hectares that make up the Copperwood project, while it has option agreements on three other targets adjacent to the project.

The project carries a sliding 2% to 4% net smelter return royalty based on the price of copper.

Helping to cover development costs, Orvana continues to produce gold from its Don Mario mine in Bolivia, with 6,545 oz. produced in the third quarter. Gold production dropped by 49% compared to the same period last year after the higher-grade Lower Mineralized Zone was mined out and the company started mining the lower-grade Las Tojas deposit. The company continues to prepare the Upper Mineralized Zone at the project for production.

Orvana’s share price climbed 34¢ or 17.7% in two days of trading following the latest news to close at $2.26, a 52-week high. The company hit its 52-week low of 82¢ in November and has 116 million shares outstanding.

Print

Be the first to comment on "Orvana rises on Copperwood PEA (September 14, 2010)"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close