Mosquito Outlines Mega-Moly Mine


VANCOUVER — The Cumo deposit has been dubbed the largest unmined, open-pit molybdenum project in the world. And now Mosquito Consolidated Gold Mines (MSQ-V, MQCMF-O) has released a scoping study outlining how it would mine it.

The project, 15 km southwest of Idaho City, is undoubtedly large. The scoping study considers the economics of the Cumo project at four mining rates between 45,000 tonnes and 181,000 tonnes per day, projecting initial capital costs in the range of US$1.6 billion to US$3.4 billion.

Mosquito puts the focus squarely on evaluating the project at mid-sized mining rates. In a 91,000- tonne-per-day scenario, Mosquito pegs startup costs at US$2.2 billion. With a 40- year mine life, Cumo returns a net present value (NPV) of US$10 billion and an internal rate of return (IRR) of 29%.

A larger, 136,000-tonne-per- day mine, would give somewhat better economics. At that mining rate the project, which would initially cost US$2.8 billion to build, has an NPV of US$16 billion and an IRR of 36%.

Based on US$16-per-lb. molybdenum oxide, US$2.10-per-lb. copper, US$12-per-oz. silver, US$6-per-gram rhenium and US$148-per-tonne sulphuric acid, payback in the mid-and larger-scale scenarios, would respectively come after 2.3 years and three years of mining.

In all scenarios, the bulk of capital costs comes from the price of building a mill — respectively US$1 billion and US$1.5 billion at the 91,000-tonne-per-day and 136,000- tonne-per-day mining rates — and the cost of pre-stripping development. In the respectively lower and higher mining-rate scenarios, Mosquito estimates prestripping costs at US$700 million and US$640 million.

The scoping study pegs cash costs per lb. moly oxide at an attractive price point: US$3.90 at the 91,000-tonne-per-day mining rate and US$4.30 at the 136,000-tonne-per- day mining rate.

The scoping study treats as ore 598 million tonnes of Cumo’s indicated resource grading 0.11% moly oxide and 0.06% copper.

Mosquito exploration manager Shaun Dykes says he has been getting two main questions about the project: “US$2.2 billion. Where are you going to get that? And then, can you get it permitted?”

On the first front — money — Dykes says that with the scoping study complete and the positive economics therein, he believes funds will soon flow.

He notes that the company recently welcomed aboard a Chinese investor, Hongxue Fu, who apparently has deep pockets. In June, Fu, through his company International Energy and Mineral Resources Investment Co. (IEMR), bought a 15% stake in Mosquito through a two-tranche private placement that saw Mosquito issue IEMR about 9.1 million shares at 35¢ apiece.

Though Dykes admits details about Fu are scant — and subject to confidentiality agreements — he says Fu is a billionaire and could very well invest more in Mosquito. At this point, with the scoping study sketching out Cumo’s favourable economics, Dykes says sourcing more cash, either through Fu or another investor, “becomes a matter of wheeling and dealing and a question of ‘what do (we) have to give up?'”

Dykes says Fu, who is now the chairman of Mosquito’s board, decided to invest in Mosquito the day after he met with the company’s management. The Beijing-based investor, Dykes says, had been looking for attractive base metal projects.

Part of the reason Mosquito made Fu chairman, Dykes says, is so that he can represent the company in China, where titles are particularly important.

As for environmental issues, Dykes does not foresee insurmountable obstacles. Mosquito is two years into base-line studies it will need for environmental permitting and has already begun to forge a relationship with environmental groups and concerned stakeholders in Idaho.

Dykes notes that preliminary metallurgical studies suggest the project’s tailings would not be acid-generating. He also points out that Thompson Creek Metal Co.’s (TCM-T, TC-N) Thompson Creek moly mine is nearby — so locals are familiar with the impact of large mines — and that in Idaho the company has developed a good reputation as a responsible corporation.

Though the Cumo project is on federal Forest Service lands, which means a rigorous permitting process is inevitable, Dykes points to the success story of Formation Capital’s (FCO-T, FCACF-O) Idaho Cobalt project. Formation Capital completed the federal environmental impact assessment process, fully permitting its project on U. S. Forest Service land, and was also able to convince state environmental groups not to oppose the project.

On news of the scoping study, Mosquito shares shed 15¢ to close at $1.27 apiece. But Dykes believes the fall was a matter of “buy on rumour and sell on news.” Since mid- September, Mosquito’s stock has posted steady gains, climbing from under 75¢ to nearly $1.50.

Mosquito has just shy of 59 million shares outstanding.

Print

 

Republish this article

Be the first to comment on "Mosquito Outlines Mega-Moly Mine"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close