Maritime releases positive results for Hammerdown gold project, with 48% post-tax IRR

The Hammerdown project. Credit: Maritime Resources

Maritime Resources (TSXV: MAE) has released the feasibility study results for its 100% owned Hammerdown gold project located in the Baie Verte mining district of Newfoundland and Labrador. The study supports a technically straightforward, brownfields open pit mine and gold processing operation benefiting from low capital investment and rapid payback.

Over an estimated five-year life, the Hammerdown mine would produce a total of 247,000 oz. of gold, averaging 50,000 oz. annually. The open pit has a run-of-mine grade of 4.46 grams gold per tonne, with 1.9 million tonnes of ore scheduled to be mined. Mineral processing will be done at the Nugget Pond mill facility, using Maritime’s 700 tonne-per-day gold circuit.

The study incorporated an updated resource estimate for the Hammerdown deposit, which now totals 2.85 million measured and indicated tonnes grading 3.61 grams gold (330,000 oz. contained) in pit. The inferred resource is 302,000 tonnes at 1.31 grams gold (13,000 oz. contained).

The report gave the Hammerdown project an after-tax net present value of $102.8 million (at 5% discount), with a 48.1% internal rate of return. The project’s initial capital cost is estimated at $75 million, with $4.9 million in net sustaining capital. Assuming a base case gold price of US$1,750 per oz., its payback period would be 1.7 years.

According to Maritime, the “attractive financial return profile” indicated in the study enables the company to pursue mine life extensions and follow up on exploration opportunities — including the Orion deposit — within its 400-sq.-km land package.

“The completion of the Hammerdown gold project feasibility study is a positive step forward for the company and positions Hammerdown as one of the highest-return, highest-grade open pit development projects located in a top-tier jurisdiction with tremendous exploration upside. We view Hammerdown as a great starter mine for the company with an average of 50,000 oz. of annual gold production and $41.4 million of annual free cash flow,” said Garett Macdonald, Maritime’s president and CEO.

“There is excellent potential to add to the project’s mine life through near-mine exploration along a 5 km magnetic low trend that has been identified adjacent to the Hammerdown deposit and also the nearby Orion deposit. Our next drill program will focus on this area, targeting shallow open-pit mineralization with the potential to be brought into the mine plan in the future,” Macdonald added.

The next step for the Hammerdown project is site construction, which Maritime is planning to start in the first quarter of 2023 and anticipates will take 12 months. First gold production is expected in early 2024. The company is now moving forward with the construction capital financing process.

Maritime shares were trading at 5¢ at noon on Wednesday, the same position the equity has been sitting at for most of the past month, and in a 52-week window of 4¢ and 15¢. Its market cap is $20 million.

Print

Be the first to comment on "Maritime releases positive results for Hammerdown gold project, with 48% post-tax IRR"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close