Goldcorp doubles gold reserves at Cerro Negro (April 25, 2011)

Goldcorp's Cerro Negro gold project in Argentina. Photo by GoldcorpGoldcorp's Cerro Negro gold project in Argentina. Photo by Goldcorp

The world’s second-largest gold producer by market value, Vancouver-based Goldcorp (G-T, GG-N), has announced a major update for its promising Cerro Negro gold project in Argentina. 

The company has released an updated feasibility study for Cerro Negro, from which it expects average annual gold production of 550,000 oz. during the first five years of commercial operations. Average cash costs during those years are predicted to be less than US$200 per oz. 

“The positive results in this feasibility study confirm our expectations that Cerro Negro will contribute tremendous value for shareholders as Goldcorp’s next cornerstone gold mine,” said Chuck Jeannes, Goldcorp’s president and CEO, in a press release.

“Capital cost estimates reflect more than a doubling of throughput, and the straightforward nature of the project design should result in a smooth construction period toward first gold production in just over two years.”

Anticipated mill throughput has increased to 4,000 tonnes per day with gold production over the full 12-year mine life, based only on existing reserves, expected to average 340,000 oz. per year at cash costs of US$290 per oz. 

Goldcorp recently more than doubled the reserve estimate for Cerro Negro, which currently stands at 13 million tonnes grading 10.19 grams gold per tonne for 4.26 million gold oz. The project hosts another 1.1 million oz. in the measured, indicated and inferred categories at lower grades.

As a high-grade epithermal deposit, Cerro Negro also contains significant silver, including 13 million reserve tonnes of 86.3 grams silver per tonne for 36.16 million silver oz.

Goldcorp acquired the property in late 2010 when it bought Andean Resources for $3.6 billion in cash and stock. At the time, Andean had delineated a 2.54-million-oz. indicated gold resource on the 215-sq.-km property.

The deposit currently comprises six known veins with significant gold and silver reserves, including Eureka, Mariana Central, Mariana Norte, San Marcos, Bajo Negro and Vein. While the Vein zone is planned as an open pit, the others will need to be accessed by separate declines. At the Eureka vein, Goldcorp has already advanced the decline to a depth of around 900 metres. Construction of declines at two other zones is expected to begin in the fourth quarter.

Goldcorp plans to spend US$130 million of the project’s US$750-million initial capital cost in 2011. This will include site access work, camp expansion, geotechnical drilling of the tailings area and plant facilities, power line design and further engineering studies. It will also include US$19 million of exploration drilling, with up to 10 drill rigs on site by late June. The drilling will focus on expanding the three zones scheduled for first production and test several new prospective veins on the western portion of the property. 

Goldcorp has already received environmental permitting for the project, but expects to update the permits soon to allow for the increased mill throughput.

On April 6 in Toronto, Goldcorp’s shares closed up 43¢ at $50.73 on the reserve news.

Print

Be the first to comment on "Goldcorp doubles gold reserves at Cerro Negro (April 25, 2011)"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close