Gold Reserve revises plan for Brisas mine

Drilling by Gold Reserve (GLDR-T) has increased proven and probable reserves at the Brisas gold-copper deposit in southeastern Venezuela.

As a result of the 13-hole, 5,700-metre program, the reserve figure stands at 6 million oz. gold and 732 million lbs. copper within 245.5 million tonnes grading 0.77 gram gold per tonne and 0.13% copper. The estimate was calculated using a gold price of US$300 per oz., a copper price US80 cents per lb. and a stripping ratio of 1.6-to-1.

Using a gold price of US$335 per oz. and a copper price of US90 cents per lb., the estimate rises to 6.9 million oz. and 900 million lbs.

Cash operating costs are pegged at US$169 per oz., based on a revised open-pit mine plan that includes an on-site copper recovery circuit.

The estimated capital cost is US$344 million.

Gold Reserve has US$10 million in cash and no long-term debt.

Print

Be the first to comment on "Gold Reserve revises plan for Brisas mine"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close