The pressure to expand is prompting senior mining companies to seek out huge, low-cost orebodies that will give them a leg up on their competitors.
Around the world, Canadian miners are pumping hundreds of millions of dollars into “mega-projects,” even as the price of most commodities sinks to historic lows.
The risks associated with these aggressive deals are great, but the risks of maintaining the status quo are even greater.
“The world has changed again,” said
In 1997, Inco won the right to develop the rich Voisey’s Bay nickel deposit for US$4.3 billion, the highest price ever paid for a mining property. Although development is being prevented indefinitely by a stand-off between Inco and the government of Newfoundland, the world’s largest nickel miner still regards Voisey’s Bay as vital to its future.
Executives of other senior producers are expressing sentiments similar to Sopko’s, and most have equally lofty plans for growth.
To meet these targets, the majors must explore for or acquire large, shallow deposits that are easy to process.
One of the biggest in this category is the Antamina deposit in the Andes mountains, about 380 km northeast of Lima, Peru. The project, co-owned by
Once the mine is up and running in early 2002, it is expected to churn out 600 million lbs. copper and 360 million lbs. zinc annually at relatively low cash costs of about US35 cents per lb. copper.
Somewhat smaller in scope is the Pascua project in neighbouring Chile, where Barrick is spending US$950 million to bring a multi-million-ounce gold deposit into production. Pascua is expected to start producing in 2002 at the rate of about 675,000 oz. gold per year.
Barrick has been among the most aggressive North American companies in its quest for growth. In 1996, the gold producer bought Arequipa Resources, owner of the Pierina deposit in Peru, which is now a 750,000-oz.-per-year producer. In 1997, the ill-fated Bre-X Minerals, once thought to control the world’s largest gold deposit, was briefly the target of Barrick’s affections. Last year, the company joined forces with
Placer Dome is also betting on Africa as a centre for growth. In early 1999, the Canadian gold miner formed a joint venture with South Africa’s Western Areas to develop the South Deep orebody, the largest undeveloped gold deposit in the Witwatersrand Basin. Placer Dome Spokesman Hugh Leggatt says the project requires US$300 million in additional capital in order for the shaft to be deepended to 3 km and for full production of 750,000 oz. to be reached by 2002.
Meanwhile, Placer is in the final stages of arranging financing for its Las Cristinas gold deposit in Venezuela, which is expected to produce an average of 450,000 oz. per year, beginning in 2001.
In the base metal sector, Rio Algom stands out as one of the most growth-oriented companies. It has three copper-zinc mega-projects slated for development: Antamina in Peru; Spence in Chile; and Crandon in Wisconsin.
Rio is currently performing bulk metallurgical tests to determine the best way to process the mixed oxide and sulphide ore at Spence, and is in the midst of a lengthy permitting process at Crandon.
If all goes well, Spence will be ready to enter production in 2002 — the same year Antamina is scheduled to start up. The rich deposit, discovered by Rio’s exploration team, will provide the company with an additional 136,000 tonnes of copper on an annual basis. Crandon will follow, once permitting and construction are complete.
Meanwhile,
Meanwhile, rival nickel miner Inco will remain in limbo until talks resume on Voisey’s Bay and until tests on the pressure-leach technology for the Goro nickel laterite deposit in New Caledonia are complete. Inco will begin on-site testing and staff training this summer in preparation for a production decision on Goro next year, a spokesman said.
Be the first to comment on "EXPLORATION 1999 — Senior producers bulk up with mega-projects — Antamina, Pascua among properties with large-scale promise"