Expensive Cigar to be lit up in 2010

The Cigar Lake uranium project will go over $1 billion thanks to delays and changes to the project design, but remains economic, says operator Cameco (CCO-T, CCJ-N).

The mine is now scheduled to go into production in 2010, rather than the 2008 starting date that had been in the plans when a rock fall and groundwater inflow made the deposit inaccessible in October 2006. Cameco and its partners — Areva (ARVCF-Q), with 37%, Idemitsu Uranium Exploration Canada, with 8%, and the Tokyo Electric Power Company, with 5% — incurred $10 million in remediation costs in 2006 and are budgeting for $74 million in 2007 and another $18 million in 2008; Cameco’s share is half of that sum.

A report on the revised development costs, which Cameco expects to make public late in the month, puts the capital cost of the project at $1,016 million. To date, the partners have spent $468 million on construction, not counting the remedial work to deal with the flooding. Cameco is also carrying $378 million in previous expenditures on its books.

The first phase of the remediation program — drilling 14 holes to allow concrete to be pumped into the flooded workings and seal off the flooded area — is nearly done. Concrete plugs are expected to be complete in the third quarter of the year.

Successive phases in the remedial plan — dewatering the workings, installing a freezing system to prevent further infiltration, rehabilitating any damaged workings, and reinstalling mine infrastructure — will require approvals from the Canadian Nuclear Safety Commission and agencies of the Saskatchewan government. Cameco says it hopes to wrap that up by the summer of 2008.

Even with the increased capital cost, the project is expected to remain economically robust thanks to very high grades. The proven reserve at Cigar is 497,000 tonnes grading 20.67% U3O8, and a minor probable reserve — 61,000 tonnes at 4.9% — has been moved back into indicated resources.

Cigar is scheduled to produce 3 million lb. (1,360 tonnes) U3O8 in 2010, rising to 9 million lb. (4,100 tonnes) in 2011 and reaching steady-state full production in 2012. It should then produce about 18 million lb. (8,200 tonnes) annually, with Cameco’s share 9 million lb.

Without Cigar Lake, Cameco is slated to produce between 21.6 million lb. (9,800 tonnes) and 23.1 million lb. (10,500 tonnes) U3O8 annually between 2007 and 2011. Cameco management said the additional capital cost of the Cigar project would not affect programs at other projects, and that the additional production from Cigar in the last two years of that period could simply be added to those projections.

Cameco has no plans to declare force majeure on any of its sales contracts.

Print

Be the first to comment on "Expensive Cigar to be lit up in 2010"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close