Wolfden boosts resources at Pickett Mtn base metals project in Maine

The Pickett Mountain base metal project in Maine is heavily forested. Credit: Wolfden Resources.

Wolfden Resources (TSXV:WLF) has released new resource numbers for its Pickett Mountain base metal project in Penobscot Cty., Maine. Both indicated and inferred resources have been significantly increased by 22% and 57%, respectively,  from a previous estimate completed in 2020.

The indicated resource is now 2.7 million tonnes averaging 8.91% zinc, 3.83% lead, 1.22% copper, 97.2 grams silver per tonne, and 0.8 gram gold per tonne (17.72% zinc-equivalent). The inferred portion is now 3.6 million tonnes at 9.27% zinc, 3.83% lead, 1% copper, 105.4 grams silver per tonne, and 0.7 gram gold per tonne (17.65% zinc-equivalent). The deposit remains open at depth and into the footwall to the north.

Both the 2021 and 2020 resource estimates were completed using the same methodology, parameters and metals prices (US$1.20/lb. zinc, $2.50 per lb. copper, US$1 per lb. lead, US$16 per oz. silver, and US$1,200 per oz. gold using a 7% base case cutoff grade of 7% zinc-equivalent.

Wolfden is pleased with the steady progress and increase in resources without changing what are conservative metals price assumptions, said president and CEO Ron Little in a news release. “The project continues to demonstrate its potential to be a significant economic driver in a region that has seen little development and job creation in the last decade,” he noted.

The Pickett Mountain property shares its geology with the Bathurst-Brunswick (New Brunswick) and the Buchans (Newfoundland) base metal camps. All are part of the Ganderia Terrain, which in Maine is both “heavily underexplored and underdeveloped,” according to Wolfden.

The company produced a preliminary economic assessment for Pickett Mountain in September 2020. The bulk of the resources sit in narrow veins, which is amenable to raise platform mining. Access to the mining areas will initially be via decline, but a shaft and production hoist may be added. A conventional 1,200 tonne per day concentrator is to be built.

Wolfden foresees an initial capital expenditure of US$147 million to develop a project with a life of just under ten years (9.7 years). Sustaining capital would add a further US$100 million and reclamation and closure another US$13.7 million.

The after-tax economic analysis includes a net present value with an 8% discount of US$198.3 million and an internal rate of return of 37%. The payback period would be 2.4 years. If the NPV were given a 5% discount rate, it would be US$255.5 million.

 

Print

Be the first to comment on "Wolfden boosts resources at Pickett Mtn base metals project in Maine"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close