Thor Explorations expects first gold pour at Segilola by end of July

Thor expects first gold pour at Segilola by end of JulyAn aerial view of the Segilola project. Credit: Thor Explorations.

Thor Explorations (TSXV: THX; LSE: AIM) has announced that commissioning of the gold processing plant at its wholly owned Segilola gold project in Nigeria has begun, and confirmed it expects to pour the first gold by the end of July. 

The process plant is being commissioned in phases, with commissioning already underway at the power plant. Commissioning of the SAG & ball mills will follow.

Mining has already begun, with 700,000 tonnes of waste mined and 30,000 tonnes of ore stockpiled in preparation for process plant commissioning. The open pit is fully prepared for mining operations with pre-strip nearing completion.

The mining fleet is fully commissioned, and production is expected to quickly ramp up to its design capacity, Thor stated in its July 19 news release.

All the necessary permits are in place and blasting operations have started as the company moves into the harder transitional and fresh ore zones.

The remaining work on the project is focused primarily on the gold room, elution and electrowinning circuit, power connection, instrumentation and control installations.

 The Africa-focused company has a market capitalization of $186.9 million.

Print

Be the first to comment on "Thor Explorations expects first gold pour at Segilola by end of July"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close