Champion Iron commissions Phase II project ahead of schedule, completes first shipment

Bloom Lake mining complex. Credit: Champion Iron

Champion Iron (TSX: CIA; US-OTC: CIAFF) has completed the first rail shipments containing 24,304 tonnes of high-grade 66.2% Fe iron ore concentrate from the Phase II expansion project at the Bloom Lake mine in Quebec.

The mine complex is located approximately 13 km north of Fermont, and 10 km north of the Mont Wright iron ore mining complex belonging to ArcelorMittal Mines Canada. The Bloom Lake mine facilities include a railway that ensures transport of the iron concentrate to a loading port in Sept-Îles.

The Bloom Lake operations were first commissioned in 2018, starting with the Phase I project that had a nameplate capacity of 7.4 million tonnes of 66.2% Fe iron ore concentrate per year over a mine life of 21 years. A Phase II expansion has since been proposed to double the existing nameplate capacity to 15 million tonnes per annum.

According to a feasibility study released in 2019, the Phase II project would require the construction of a concentrator plant, which was partially built by the mine’s former owner, and an optimized mine plan to accelerate the supply of ore to the expanded facilities while maintaining a mine life of 20 years.

The study evaluated a total preproduction capital expenditures of $633.8 million, including deposits. As of Mar. 31, a total of $625.2 million, including deposits, has been invested in the project.

Commissioning of the Phase II project was recently achieved ahead of schedule, and the company is now working to gradually increase the mine and plant’s capacity towards commercial production, anticipated to occur by the end of this year.

“The Phase II project is expected to be in operation for decades and will provide the Québec Côte-Nord region with over 400 additional permanent high-quality jobs. Completing the project ahead of schedule, while facing the challenges imposed by the Covid-19 pandemic, is a testament to the agility and operational excellence of our employees and partners,” Champion’s CEO David Cataford commented in a news release.

Print

Be the first to comment on "Champion Iron commissions Phase II project ahead of schedule, completes first shipment"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close