Solid Economics For Northgate’s Young-Davidson Project

Drilling underground at Northgate Minerals' Young-Davidson gold project, near Matachewan in the Abitibi greenstone belt of Ontario.Drilling underground at Northgate Minerals' Young-Davidson gold project, near Matachewan in the Abitibi greenstone belt of Ontario.

The verdict of a final feasibility study on Northgate Minerals’ (NGX-T, NXG-X) Young-Davidson project in northern Ontario confirms a healthy rate of return over a 15-year mine life with average annual production of 180,000 oz. gold at a net cash cost of US$351 per oz.

The mining operations will consist of an open pit and underground mine. After the first two years of open-pit production, average annual production for the remaining life of the mine will climb to 190,000 oz. gold from underground at a net cash cost of US$341 per oz.

Cash costs of production are anticipated to fall below the industry average because of the project’s good geometry, the orebody’s strong continuity and thickness, and the competency of the host rock, which enables the company to use low cost bulk-mining techniques, Northgate explains.

The Young-Davidson property sits on the site of two past-producing mines that yielded about one million oz. of gold between the mid-1930s and the mid-1950s.

The property is about 3 km west of the town of Matachewan in the Abitibi greenstone belt, and about 60 km west of Kirkland Lake.

Initial capital costs have been estimated at US$339 million, with sustaining capital costs over the life of the mine of US$236 million.

The final feasibility study, which comes on the heels of the pre-feasibility study completed in July 2009, was based on proven and probable gold reserves of 2.8 million oz. gold and calculated using a gold price of US$825 per oz. and an exchange rate of US$1 to 90¢ Canadian.

The project economics did not include the 6 million tonnes of inferred resources and 132,000 tonnes of indicated resources.

The project should yield a pretax operating cash flow of US$646 million, a 5% net present value of US$264 million and an internal rate of return of 12.4%.

Production is forecast to begin in 2012.

The facilities will include a modern 6,000-tonne-per-day process plant utilizing conventional gold processing technology.

Access to the underground mine will be via a ramp, and the company plans to deepen the existing shaft and develop a new production shaft.

Dewatering activities and ramp development resumed at the site during the last quarter of 2009, to advance exploration and set up the underground access conditions needed to build the new production shaft.

Rather than sinking a new production shaft from surface, the company has decided to deepen the existing Matachewan Consolidated mine shaft from 775 metres to 1,515 metres and raise a new main production shaft in two sections from the bottom of the known reserve at 1,515 metres.

Nearly US$7-million worth of underground equipment that is needed to develop the ramp has been ordered and is scheduled to arrive before April.

Electric power for the site will be supplied by upgrading about 47 km of an existing 115-kilovolt power line and installing 7 km of a new 115-kilovolt line from Kirkland Lake to Matachewan Junction and a mine site transformer station.

Currently the open-pit zone has probable reserves of 4.94 million tonnes grading 1.66 grams gold per tonne for contained gold of 264,000 oz. The underground zone has proven reserves of 3.47 million tonnes grading 3.22 grams gold for contained gold of 359,000 oz. and probable reserves of 22.74 million tonnes grading 2.92 grams gold for 2.14 million oz. gold.

Additional work is expected to upgrade resources into the reserve category.

The Young-Davidson orebody remains open down-plunge below existing reserves and resources.

Northgate and the Matachewan First Nation signed an impact and benefits agreement on July 2.

The gold and copper producer has mining operations, development projects and exploration properties in Canada and Australia and is forecasting gold production of 316,000 oz. and copper production of 47.6 million lbs. in 2010.

In Toronto, Northgate is trading at $3.12 per share and has a 52-week trading range of $1.21-$3.70 per share. The company has 290.5 million shares outstanding.

Print

 

Republish this article

Be the first to comment on "Solid Economics For Northgate’s Young-Davidson Project"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close